The International Energy Agency's *Electricity 2026* report shows that global solar photovoltaic power generation increased by 620 TWh year-on-year in 2025, and projects that the share of low-emission energy sources (led by renewables such as solar and nuclear) in global electricity generation will rise from 42% in 2025 to 50% by 2030. The large-scale grid integration of new energy sources has created rigid demand for power transmission and transformation infrastructure.
The International Energy Agency's Electricity 2026 report shows that global solar photovoltaic power generation increased by 620 TWh year-on-year in 2025, and projects that the share of low-emission energy sources (led by solar and nuclear power) in global electricity generation will rise from 42% in 2025 to 50% by 2030. The large-scale grid integration of new energy has created rigid demand for power transmission and transformation infrastructure. From a general contractor's perspective, this article reviews the market opportunities, technical challenges, and management requirements in the international power transmission and transformation engineering sector driven by new energy development, and proposes corresponding capability-building pathways.
Market Opportunities in Power Transmission and Transformation Engineering Driven by New Energy Delivery
The source-load separation characteristic of new energy development determines that transmission corridor construction is not an optional demand driven by policy advocacy, but a rigid prerequisite for the large-scale development, grid integration, and consumption of new energy. Looking at regional new energy development trends globally, the power transmission and transformation engineering market exhibits distinct regional characteristics and growth potential.
I. Europe: Offshore Wind Driving Large-Scale Investment in Transmission Infrastructure
In January 2026, Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway, and the United Kingdom signed the North Sea Offshore Wind Investment Agreement in Hamburg, confirming the target of building 300 GW of offshore wind capacity in the North Sea by 2050, and committing to add 15 GW of new offshore wind capacity annually between 2031 and 2040. The governments committed to listing bilateral contracts for difference (CfDs) as the standard mechanism for offshore wind auctions, aiming to reduce financing costs and stimulate market investment activity.
II. Middle East: Large-Scale Clean Energy Bases Spurring Cross-Border Transmission Corridors
In early 2026, the 1,500 MW Al Hazna solar PV EPC project in Abu Dhabi, UAE, was fully launched, encompassing a 1,807 MW (DC side) PV plant area, a 33 kV/400 kV substation, a 400 kV switchyard, and 25 km of 33 kV overhead transmission lines. The project is expected to meet the electricity needs of approximately 160,000 households in the UAE.
III. Southeast Asia: Regional Grid Interconnection Moving from Vision to Engineering Practice
Laos' Monsoon 600 MW wind power project delivers electricity generated in Laos to Vietnam via an approximately 22 km cross-border transmission line, with a total investment of US$950 million. As Asia's first new energy project with cross-border power transmission and the largest single wind power project in Southeast Asia, the project achieved grid connection of its first turbine units in 2025, with the Phase II 1,000 MW project now in the planning stage. In April 2026, the Asian Development Bank launched the Southeast Asia Energy Regional Interconnection Fund, dedicated to financing preparatory work for ASEAN grid cross-border transmission projects. The Bank has committed up to US$10 billion over the next decade to support the ASEAN Power Grid and related investments.
IV. Central Asia: Wind and Solar Power Export Opening New Transmission and Transformation Markets
The Kazakhstani government plans to increase the share of renewable energy in power generation to approximately 15% by 2030 and further to 50% by 2050. GlobalData forecasts that Kazakhstan's renewable energy installed capacity will grow from approximately 3.5 GW in 2025 to approximately 12.9 GW by 2035, with onshore wind expanding from approximately 1.9 GW to nearly 8.7 GW and solar PV from approximately 1.3 GW to approximately 3.7 GW. Kazakhstan's national grid operator KEGOC has approved a national grid development strategy through 2035, aimed at enhancing transmission capacity and integrating renewable energy resources. KEGOC is advancing two core grid upgrade projects: first, the construction of the "Almaty–Zhambyl" north-south transmission corridor, adding 475 km of 500 kV transmission lines; and second, integrating the western regional grid into the national unified power system through the construction of 604 km of 500 kV transmission lines. Uzbekistan plans to increase renewable energy installed capacity to 25 GW by 2030, of which wind power targets 5 GW, with renewable energy expected to account for approximately 40% of power generation.
It is evident that new energy delivery is driving market opportunities in the power transmission and transformation sector.
Key Challenges
I. System Adaptability Dilemmas Arising from Output Characteristics
The intermittency and volatility of new energy generation create fundamentally different operating conditions for transmission systems compared to conventional power sources. Taking wind power as an example, annual utilization hours typically range from 2,000 to 3,000 hours, meaning the capacity utilization of transmission corridors is naturally lower than that for conventional power plants. On the other hand, the extreme output of new energy can instantaneously approach installed capacity; if transmission capacity reserves are insufficient, there is a risk of wind and solar curtailment. This contradiction is particularly acute in large-scale wind and solar power base export projects in desert, Gobi, and barren areas.
II. Profound Changes in Fault Transient Characteristics
The more challenging issue lies in the transient behavior during faults. Conventional synchronous generators possess substantial rotational inertia and can provide stable short-circuit current support after faults. In contrast, new energy units connected to the grid via power electronic interfaces typically have fault currents limited to 1.2–1.5 times rated current and are governed by fast-responding control systems. This weak-infeed characteristic threatens the effectiveness of traditional protection principles based on power-frequency electrical quantities. In one overseas wind power delivery project, an external fault triggered a cascading disconnection event when the sending-end wind farm's low-voltage ride-through control strategy was improperly coordinated with the DC system's protection settings. This lesson demonstrates that new energy power transmission projects can no longer treat generation units simply as power sources—they must be incorporated into a unified control and protection framework for the entire transmission system and designed holistically.
III. Strong Coupling Between Environmental Factors and Operating Conditions
Regions rich in new energy resources are often characterized by harsh natural environments. Offshore wind farms face risks from high salt spray, severe typhoons, and ship collisions, while wind and solar bases in desert, Gobi, and barren areas face risks from high winds, sandstorms, and extreme diurnal temperature variations. These environmental factors not only influence equipment selection but also form a strong coupling with the actual transmission capacity of power lines. In conventional line design, transmission capacity is determined by static thermal stability limits, taking the most severe environmental conditions as the design basis. In reality, however, high-wind conditions often improve heat dissipation, enabling line current-carrying capacity to increase by 30%–50% compared to still-air conditions. The high correlation between periods of peak new energy generation and high-wind, strong-sunlight weather provides a physical foundation for dynamically exploiting transmission potential.
IV. Evolution of Technical Routes and Equipment Suitability Requirements
Conventional line-commutated converter (LCC) HVDC technology is mature and cost-effective, but it relies on AC grid commutation and is prone to commutation failures in weak-grid scenarios with high penetration of renewable energy; its applicability is narrowing. Voltage-source converter (VSC) HVDC technology, which does not require AC grid support and can independently regulate active and reactive power while constructing passive networks, has become the preferred technical choice for new energy delivery.
New energy transmission and transformation imposes three new requirements on equipment: higher voltage levels, compact design, and extreme-environment adaptability. For example, deep-sea offshore wind delivery has already risen to ±500 kV, with even higher voltage levels such as ±800 kV ultra-high-voltage VSC-HVDC under planning. Given the limited space on offshore platforms and in desert and Gobi regions, equipment layout must be extremely compact. Gas-insulated switchgear (GIS) replacing open-type equipment has become an inevitable trend. Offshore platforms adopting GIS, prefabricated cabins, and an integrated "AC-DC" three-dimensional layout can reduce footprint by 40%–50% and shorten construction periods by 40%. To withstand high salt spray, severe typhoons, and sandstorms, equipment must pass 1,440-hour salt spray tests, IP65 protection ratings, and sandstorm tests. Notably, Pinggao Electric's DC wall bushing has been applied in Brazil's ±800 kV transmission project and verified by the International Electrotechnical Commission (IEC).
Given the above, general contractors must establish equipment specifications that exceed common standards and become deeply involved in manufacturing quality control.
V. Core Risks and Hidden Costs
New energy transmission and transformation projects generally face completion risks, cost overrun risks, and performance risks. In addition, two hidden costs are becoming increasingly prominent.
The first is the lack of standards-setting influence. PPP projects led by European and American investors often mandate IEC or European/American standards, forcing Chinese general contractors to bear additional conversion costs. In 2025, China led the release of two IEC DC switchgear standards, but their adoption will take time. In practice, many Chinese general contractors have begun proactively providing cross-reference tables between IEC and equivalent Chinese standards during international project bidding, recommending national standards to reduce friction.
The second is localization constraints. In one wind power project in Oman, for example, the local content requirement is no less than 20%, with locally sourced products costing 20% more and requiring delivery lead times three months longer. To meet localization requirements, companies must secure local production capacity in advance while maintaining domestic buffer stock—this "double insurance" arrangement increases direct costs. If such costs are not adequately estimated at the bidding stage, they can directly lead to project losses. Regarding labor, apart from core positions staffed by Chinese personnel, the majority of workers are local hires to accommodate localized operations.
Recommendations
I. Strengthening Forward-Looking Technical Route Assessment Capability
In international engineering practice, a common misconception is confining technical decision-making to the design phase, treating subsequent procurement, construction, and commissioning as mere "execution per drawings." However, in the new energy sector, technological progress advances rapidly, and the selection of key equipment often directly determines the feasibility of the overall system solution. This requires general contractors to establish an integrated multi-disciplinary coordination mechanism covering design, procurement, and construction in the early project stages, keeping control of key technology decisions firmly in their own hands. Therefore, general contractors must secure decision-making authority over key equipment selection in the early project phase to avoid being placed in a passive position later.
II. Enhancing Technical Integration Capability
The traditional linear "design-procurement-construction" model is ill-suited to new energy projects. Technical integration capability is the ability to synthesize professional expertise, equipment characteristics, construction conditions, and operational requirements into a systematic solution, comprising three levels.
First is cross-disciplinary technical coordination and integration. The design phase must handle the coupling of multiple disciplines—power systems, structural, communications, and protection—in parallel. For instance, in offshore wind VSC-HVDC projects, the dimensions, weight, and heat dissipation requirements of converter valves directly influence the structural design of offshore platforms and the selection of construction vessels; the bending radius and installation tension of DC cables constrain route selection and laying schemes. These coupling relationships must be coordinated from the earliest design stages; otherwise, late-stage changes will result in substantial cost and schedule losses.
Second is the integrated closed loop of design, procurement, and construction. Technical integration capability requires breaking down barriers among design, procurement, and construction to form a closed loop of "design guiding procurement, procurement feeding back to design, and construction validating design." Design incorporates equipment parameters, procurement assesses construction feasibility—such as transport routes and on-site lifting conditions for overweight and oversized equipment—and construction feedback optimizes design, building an experience database for continuous improvement in subsequent projects.
Third is full-lifecycle data connectivity. The operations and maintenance phase of new energy transmission and transformation projects lasts 20–30 years, yet the responsibilities of traditional general contractors typically end with the warranty period. Technical integration capability requires general contractors to extend their vision across the entire project lifecycle, establishing a digital data chain from design, manufacturing, and construction through to operations and maintenance. For example, suppliers should be required to provide digital models—such as BIM models and digital twin interfaces—at the equipment procurement stage; actual measurement data for critical processes, such as cable laying tension and joint fabrication environmental parameters, should be recorded during construction; and complete system parameter setting records should be generated during commissioning. These data form a "digital delivery package" at project handover, providing the technical foundation for the owner's subsequent operations and maintenance, while also accumulating core assets for the general contractor's participation in future upgrade and renovation projects.
Building technical integration capability requires supporting organizational adjustments. First, establish a core cross-disciplinary engineering team with members from diverse backgrounds including design, procurement, construction, and commissioning, possessing systems thinking and communication and coordination skills. Second, build an enterprise-level technical knowledge base that structurally codifies lessons learned from each project into reusable design guidelines, equipment selection templates, and risk checklists. Third, develop a digital engineering platform integrating multi-disciplinary collaborative design, materials tracking, construction schedule simulation, and operations and maintenance data management.
III. Supply Chain Resilience and Dual-Sourcing Strategy
While prioritizing domestically manufactured core equipment, international backup sources should be maintained for critical components such as PV modules, inverters, wind turbines, energy storage equipment, and transformers. In countries with mandatory localization requirements, local subcontractors should be proactively cultivated—not only through procurement but also by transferring quality management systems and testing methodologies.
IV. Building Systematic Full-Cycle Risk Management Capability
Enterprises should establish risk checklists and tiered management mechanisms covering all phases—bidding, contract negotiation, construction, commissioning, and warranty—internally. A "red-yellow-green" three-tier management approach can be adopted: red items, such as risks that host-country foreign exchange controls may restrict profit repatriation, must have solutions formulated or acceptance thresholds clearly defined at the bid decision stage; yellow items, such as insufficient qualifications of local subcontractors, should be downgraded to green during the construction preparation phase; only green items may proceed to the next stage. This method is not complex, but its value lies in transforming risk management from reactive response to proactive control.
V. Extending Business Models
International new energy projects increasingly require general contractors to possess financing capability and operations and maintenance experience. On the O&M front, a dedicated local O&M company can be established, leveraging equipment operating data accumulated during the commissioning phase to provide first-year "accompaniment" services to the owner. While these extended services expand the contractor's scope of responsibility, they effectively enhance customer stickiness and create entry points for future upgrade and renovation projects.
Conclusion
In the new energy era, international power transmission and transformation projects are transitioning from mere corridor construction to the construction of energy internet hubs. Rigid market demand coexists with compressed schedules, uncertain technical routes, and rising costs from standards localization. VSC-HVDC has become the rigid technical choice in weak-grid scenarios, and the general contractor's role has extended to include financing coordination, supply chain resilience building, and long-cycle risk underwriting. In this context, technical integration capability—the systematic integration of cross-disciplinary coordination, the closed loop of design-procurement-construction integration, and full-lifecycle data connectivity—is becoming the key source of general contractors' core competitiveness. International power transmission and transformation general contractors should place technical integration capability at the core, supplemented by forward-looking technical route assessment, supply chain dual-sourcing strategies, full-cycle risk management systems, and business model innovation, to systematically rebuild their capabilities. This transformation requires sustained investment and experience accumulation. Only those enterprises that cultivate technical integration capability in depth across the three dimensions of technology, commerce, and management will seize the initiative in the new-energy-driven industry transformation and convert periodic opportunities into sustainable competitive advantages.