Abu Dhabi National Oil Company (ADNOC), established in 1971, is the state-owned oil company of the United Arab Emirates and one of the world's largest oil and gas companies. Its subsidiary, ADNOC Onshore, focuses on the exploration, development, production, and sales of onshore oilfields in Abu Dhabi, among which A oilfield and B oilfield are the two main producing oilfields of ADNOC Onshore.
Abu Dhabi National Oil Company (ADNOC), established in 1971, is the state-owned oil company of the United Arab Emirates and one of the world's largest oil and gas companies. Its subsidiary, ADNOC Onshore, focuses on the exploration, development, production, and sales of onshore oil fields in Abu Dhabi, with Oil Field A and Oil Field B being its two main producing fields. Taking the capacity upgrade EPC project of the central processing stations at the two main oil fields A and B as an example, this paper analyzes the difficulties and challenges in detailed design schedule planning management when executing onshore oilfield surface engineering projects in the UAE, summarizes the practical experience in schedule planning management gained by CPECC Beijing Design Branch as the detailed design subcontractor under the EPC general contracting model, and analyzes the issues encountered during project execution.
Project Overview
To implement its "Crude Oil Production Capacity Increase to 5 Million Barrels Per Day – P5" strategy, ADNOC has planned a series of production enhancement projects. The capacity upgrade and renovation of the central processing stations at Oil Field A and Oil Field B are key components of this strategy, aiming to increase production at both fields through the expansion of the two central processing stations, thereby meeting the P5 production targets. The project encompasses the expansion of the central processing stations at both Oil Field A and Oil Field B, characterized by the large scale of brownfield expansion, high technical standards, tight schedules, and complex interfaces. The total project duration is 39 months, undertaken by CPECC under the EPC model, with its subordinate Beijing Design Branch responsible for detailed design. Detailed design schedule planning management is the core and an important component of EPC schedule planning management, serving as the prerequisite and foundation for the orderly execution of procurement and construction.
International EPC Project Control Procedures
I. ADNOC Project Execution Phase Control Procedures
ADNOC has a complete set of project control procedures for the execution phase of onshore oilfield projects. All contractors must prepare project control procedures in accordance with these procedures, submit them to the owner in the form of a plan proposal, and execute them upon approval by the owner's management team, aiming to improve project management efficiency. These procedures mainly include six programs: project planning and scheduling, progress measurement, progress reporting, project risk management and schedule risk analysis, invoicing/payment and accounting, and change management. This paper focuses on the first two procedures related to design schedule planning and the plan proposal.
1. Project Planning and Scheduling Procedure
This includes the project calendar, work breakdown structure (WBS), and a comprehensive planning network comprising Level 1, Level 2, Level 3, and Level 4 schedules. Level 1 is the overall project master schedule, Level 2 is the project total schedule, Level 3 is the overall project schedule including the critical path, and Level 4 is the detailed schedule. The Level 4 schedule is the fundamental plan guiding design, procurement, and construction, mainly including: detailed plans for company headquarters (design) procurement and construction, S-curves (by phase/discipline/area/sub-area), manpower histograms and loading charts (broken down by phase/discipline), mechanical equipment histograms and loading charts, auxiliary schedules, and man-hour quotas.
2. Progress Measurement Procedure
Contractors shall adopt a quantified progress measurement system in accordance with the agreed work breakdown structure, covering design, equipment/material manufacturing and delivery, and construction phases. The overall weight for each project phase is specified as: design 7%, procurement 43%, construction 45%, and commissioning, temporary acceptance 5%.
3. Plan Proposal
Contractors shall prepare a plan proposal according to the specified schedule and submit it to the owner for review and approval. This proposal contains all details of the specific methods and arrangements the contractor intends to adopt for executing the contract, including planning and scheduling, cost control, manpower and construction equipment levels, and schedule arrangements.
The plan proposal needs to cover all key points of schedule development, project control schedule analysis, schedule forecasting, schedule updates and progress reporting based on the approved schedule, and corrective measures, and should cover the entire project construction cycle.
The submission timeline for the plan proposal is as follows.
(1) Four documents to be submitted within 2 weeks after contract effectiveness, including: the first 90-day look-ahead plan, project weekly progress report, work breakdown structure, and overall project Level 1 schedule.
(2) Two documents to be submitted within 3 weeks after contract effectiveness, including: design document register and project control procedures.
(3) Eighteen documents to be submitted within 8 weeks after contract effectiveness. Those mainly related to detailed design include: Level 1 schedule, project calendar, project overall Level 2 schedule, project Level 3 schedule, critical path analysis and narrative, design document register and submission plan, manpower histograms, project control procedures, planning organization structure, and schedule risk analysis.
II. Design Schedule Preparation
As an important component of the EPC project, design leads procurement and construction. Design plays a major role in the preparation of the work breakdown structure, the first 90-day look-ahead plan, and the preliminary project Level 1 schedule. The WBS is typically prepared based on the facilities shown in the overall plant layout. The first 90-day look-ahead plan mainly covers the document submission plan for all design disciplines within 90 days. The preliminary project Level 1 schedule primarily consists of milestone node plans.
The design document register plan is the core of design schedule preparation. All design documents/activities, including drawings, data sheets, specifications, deliverables generated for procurement (material requisitions, technical tender documents), and deliverables generated for construction (drawings approved for construction), should be listed in the design document register plan. Contractors shall submit a weighted register listing all deliverable documents/engineering documents along with their planned, forecast, and actual issue dates at designated stages for owner approval. Each deliverable should be weighted based on estimated man-hours/complexity. In the design document register plan, each deliverable should correspond to a schedule software (P6) activity ID, with progress aggregated to the cost-time-resource level and discipline level for progress reporting. To standardize progress reporting in the drawing/document status system, milestone patterns should be established for each document type, with each milestone corresponding to a fixed percentage of completion.
The cumulative weight for each milestone of a design document is as follows: work started, 5%; submitted for review/comment, 35%; submitted for approval, 50%; submitted for construction/implementation/procurement, 85%; approved for construction/implementation/procurement, 100%.
III. Design Schedule Control
After the EPC project schedule package is prepared and submitted to the owner for review and approval, the contractor can execute the project in accordance with the approved project baseline schedule.
Detailed design schedule control primarily uses the design document register plan as the baseline schedule, measuring actual project progress weekly and monthly, including actual progress by discipline, the number of documents submitted by each discipline, and S-curves. The monthly detailed design progress corresponding to the P6 file codes with cost-time-resource data needs to be synchronized to the EPC contractor, who then updates the P6 overall project schedule. Through design weekly meetings, EPC weekly and monthly meetings, design progress and coordination issues are reported to the owner's management team and the owner, thereby achieving design schedule control.
Detailed Design Schedule Preparation Practice for UAE EPC Projects
I. Experience Summary and Learning
Lessons learned from the design summary of the Oil Field A Phase I EPC project regarding schedule control were studied. The latest project execution phase project control procedures issued by the ADNOC Technical Center in 2023 were carefully reviewed, and the design-related content was prepared strictly in accordance with the requirements of these procedure documents.
II. Development of Design Milestone Plans
The project milestone plan was established at the early stage of the project. The Level 1 milestone node plan includes the kick-off meeting, plot plan review, design review, HAZOP review, and 30%, 60%, and 90% model review milestone plans. Through full communication with the safety discipline lead, third-party study milestone nodes were added to the Level 2 milestones, including hazard identification/environmental identification/occupational health identification, inherent safety design, safety integrity level classification, bowtie analysis, electrical design review, HAZOP study, energy study review, cybersecurity review, ALARP study, project HSE review Phase 3, and alarm system management review milestone plans. Only the design Level 2 plan incorporating the various nodes of third-party studies can meet the owner's review requirements.
III. Work Breakdown Structure Confirmation
According to the owner's requirements, considering the characteristics of the brownfield renovation project in the early project phase, and in conjunction with the project scope and overall plot plan, the project work breakdown structure was prepared and submitted to the owner for approval, to be used for the Level 2 area distribution in the design document register plan.
IV. Preparation of the Design Document Register Plan
The design document register plan was prepared strictly in accordance with ADNOC's template for detailed design projects. Based on the owner-approved project WBS, the design Level 3 schedule was developed, with man-hours referenced from the Middle East Design Center's man-hour standards. Separate man-hours were assigned to 3D modeling and model reviews.
When preparing the document registers, each discipline must list documents strictly in accordance with the scope of work in the tender documents and the depth requirements for each discipline, and submit them to the owner's management team for approval. For excessively high requirements from the owner's management team, discipline leads should fully communicate with the owner's management team to avoid over-design, which is beneficial for schedule and cost control.
V. P6 Schedule Preparation
Special meetings were held with the EPC project management team to discuss the project critical path and prepare the project Level 2 schedule. On the procurement side, the focus was on identifying the logical relationships between the timing of activities such as long-lead equipment and their inquiry requests, technical bid evaluations, purchase orders, and vendor document returns, and design activities. On the construction side, the focus was on identifying and discussing the logical relationships between design inputs for tank farms, pipe racks, steel structures, and underground pipelines, and the construction drawing schedules, as well as the interrelationships between third-party process safety studies and related disciplines such as process, plot plan, and fire protection, laying a solid foundation for the development of the Level 3 schedule.
Given that this is an EPC project, for the P6 Level 3 schedule items, the design is listed according to the cost-time-resource principle. Key design documents from each discipline and design documents related to procurement and construction are included in P6. The design portion of the P6 WBS is organized with clear area breakdowns and well-prioritized discipline plans at appropriate hierarchical levels, reserving clear paths for subsequent procurement and construction logical relationships, laying a good foundation for the overall EPC plan preparation, and providing favorable conditions for project execution schedule control after the project baseline schedule is approved.
Detailed Design Schedule Control Practice for UAE EPC Projects
After the project baseline schedule is approved by the owner, the project control team immediately uses it as the baseline for schedule control. Design schedule control is primarily achieved through the following five aspects.
I. Weekly and Monthly Reports
At the end of each week, the design document submission status summary table is downloaded through the comprehensive document management system platform. The status summary table allows filtering of the overall documents actually submitted by each discipline, the submissions made during the current week, and document statuses, including internal review, submission, inter-discipline review, owner management team engineer review, and revision status. By importing the status summary report into the design document register plan, the overall design progress, weekly progress, S-curves, and the status of documents submitted by each discipline, as well as the planned number of documents to be submitted by each discipline in the next two weeks, can be calculated. Documents not submitted as planned are raised at internal design weekly meetings, where planning engineers promptly coordinate with discipline engineers to analyze causes, develop catch-up plans, and track and implement them to ensure the timely realization of each discipline's baseline plan.
II. Tracking and Control of Procurement Support Documents
The progress of submitting discipline inquiry requisitions, issuing inquiry packages, technical bid evaluations, and placing purchase orders is critical to the subsequent return of vendor documents and is the prerequisite input determining whether the 60% model can proceed smoothly. The design team coordinates closely with the procurement team. Batching principles for inquiry requisitions, such as piping valves and various instrument gauges, were established at the project outset, along with principles for technical bid evaluations, ensuring the smooth issuance of inquiry packages and the smooth conduct of technical bid evaluations. Simultaneously, dedicated personnel are assigned to manage the vendor list affecting the 60% model inputs, dynamically tracking the return of vendor documents. For equipment foundation drawings, general equipment manufacturing drawings, and 3D models of skid-mounted equipment, the procurement and design teams work together to monitor and urge vendors to submit relevant materials as planned, ensuring that the inputs for the 60% model are in place.
III. Design Milestone Node Control
The most important aspect of design schedule control is the control of Level 1 milestone node plans. The prerequisites for the tasks at each Level 1 milestone node, such as plot plan review, design review, HAZOP review, and 30%, 60%, and 90% model reviews, should be understood in advance to ensure that prerequisites are met. Typically, a checklist approach is used to track and monitor each item, such as the prerequisite checklist for the 30%, 60%, and 90% model reviews, which is verified item by item against the baseline plan to ensure the timely completion of each milestone plan.
IV. Catch-up Plan Preparation and Tracking for Design Schedule Delays
Around the time of the 60% model review, delays in the provision of vendor documents from some equipment manufacturers affected the development of the 60% model, resulting in schedule delays for disciplines such as piping, structural, electrical, and instrumentation. For disciplines with schedule delays exceeding 5%, the project team coordinates with the relevant discipline leads to develop a catch-up plan for the next month, a weekly list of documents to be completed, and estimated progress recovery targets, followed by assessment of the actual catch-up situation. For disciplines that still fail to achieve the catch-up plan, special meetings are held, and additional discipline manpower is deployed when necessary to ensure the successful completion of the catch-up plan.
V. Innovation in 3D Model Progress Control
The ADNOC project control procedures require a detailed design 3D model schedule, with model progress measured and tracked separately for each discipline. Taking the piping discipline as an example, a schedule for each pipeline is required. To improve the efficiency of schedule planning management, in view of the work content and review key points of the three 3D model stages (30%, 60%, and 90%), the design team, after multiple research discussions, proposed a simplified 3D model progress measurement system. This system not only met the owner's schedule requirements for the 30%, 60%, and 90% 3D model review stages, but also covered the progress measurement for the five modeling disciplines—piping, structural, electrical, instrumentation, and telecommunications—at the 30%, 60%, and 90% stages. The system was approved by the owner and implemented throughout the project, saving 50% of the time spent on 3D model progress measurement calculations each week.
Conclusion
Schedule planning control for EPC projects in the international oil and gas industry is a specialized project management function, and major international oil companies each have their own project management procedures and schedule control procedure documents. Through the analysis of detailed design schedule control practices in the UAE EPC project, the ADNOC EPC project schedule control procedures have been understood and mastered. By strengthening the integration of project control and management software technology, the seriousness of project plan execution has been enhanced, and early warning management for schedule control has been strengthened, providing a reference for the smooth implementation of schedule control work in future Gulf region projects.
(Authors: Li Yachun Wu Dongyu Authors' Affiliation: CPECC Beijing Design Branch)